| June 10, 2011 |
|
Final Inspection and Completion Letter received from the Colorado Dept. of Public Health and Environment |
| Dec 13, 2010 |
The Town of Hot Sulphur Springs accepted the construction project as complete. |
| Nov 13, 2010 |
Ribbon cutting ceremony was held at the new water treatment plant. |
| October 2010 |
The new water tank, water filter and water plant began testing procedures to go into service. |
|
March 2010 |
Construction season began for 2010. |
| Dec 09 - Mar 10 |
Work on final designs and specifications progressed and equipment and materials were ordered. |
| October 2009 |
Construction began. Work was completed on the new intake structure and clear well. |
| Sept 2009 |
Garney Construction was selected as the General Contractor. Funding was secured. Groundbreaking ceremony was held. |
| Aug-Sept 2009 |
Bidding process began, contractor meetings were held, bidding closed on Sept. 3, 2009. |
|
July 2009 |
CDPHE approved the Final Plans and Specifications for construction. |
|
June 2009 |
Final Plans submitted to CDPHE. |
| |
|